PCS TG 007 Solar PV ER Calculation Tool Guide_v1.0
Document Control
Document identification
Document code: PCS-TG-007
Title: Solar PV ER Calculation Tool Guide
Scope: Guidance for completing and submitting the Solar PV ER Calculation Tool for projects applying PCS-TR-003; includes configuration selection, data requirements, evidence requirements, QA/QC checks, and VVB verification expectations
Associated methodology: PCS-TR-003 Renewable Electricity Generation – Solar Photovoltaic (PV)
Associated tool: PCS-TA-011 Solar PV ER Calculation Tool (XLSX)
Crediting outcome: Not applicable (technical guidance supporting calculation and verification)
Version history and change log
Table DC-1. Revision history
Version
Date
Status
Summary of changes
Prepared by
Approved by
v1.0
TBD
Draft
Initial release for public consultation
PCS Secretariat
TBD
Superseded versions
No superseded versions for v1.0.
Governance note on versioning and archiving
Only the latest approved version of this Tool Guide shall be used. Superseded versions shall be archived and retained for traceability and audit purposes. Printed or downloaded copies are uncontrolled; stakeholders must refer to the PCS-published version as the authoritative current version.
Chapter 1 - Community summary
1.1 What this guide is
This guide explains how to complete the PCS-TA-011 Solar PV ER Calculation Tool for projects applying PCS-MT-003 Renewable Electricity Generation – Solar Photovoltaic (PV). It explains what data to enter, what evidence is expected, what QA/QC checks must pass, and what a VVB will verify.
2.2 Why this matters
Without a standard tool, identical projects can produce inconsistent results due to different assumptions and spreadsheet logic. This tool standardizes calculations so results are reproducible, auditable, and conservative.
3.3 Who this applies to
Actor
How they use the tool/guide
Project Proponent
Completes INPUTS, DATA and EF; resolves QA/QC flags; submits outputs with Monitoring Report.
VVB
Traces values to raw evidence; checks configuration correctness; reproduces outputs from tool; raises CARs where needed.
PCS Secretariat
Checks consistency of submitted outputs with programme rules and registry records (labels, status, etc.).
4.4 What you can do vs what you cannot do
Allowed (if evidenced)
Not allowed
Use revenue-grade POI export meter totals as EG (A1/A3/A6).
Estimate EG when revenue-grade meter/settlement data exists but is not provided.
Use gross generation minus auxiliary (A2) if meters support it.
Mix boundary types within the same monitoring period without justification.
Apply PCS grid EF for correct grid and year.
Use EF from a different grid/year without PCS acceptance.
Use conservative substitutions for data gaps with documentation.
Substitute missing data in a way that inflates EG or reduces deductions without justification.
5.5 Common scenarios
Chapter 2 - Tool structure
Tab
Purpose
README
Purpose, how-to, and version control.
INPUTS
Project ID, monitoring dates, configuration, and deductions.
EF
Grid emission factor value, year, and source reference.
DATA
Monthly activity data required for EG (and PE for A2).
CALCS
Computation of EG, BE, PE, LE, ER and deductions.
OUTPUT
Final values for reporting.
QA_QC
Automated checks; all must pass before submission.
Chapter 3 - Configuration selection
Select the configuration that matches your metering boundary. Use only the DATA columns indicated for your selected configuration.
Config
When to use
DATA columns used
PE in tool
A1
POI net export meter
Net export at POI
PE = 0
A2
Gross generation minus auxiliary
Gross generation; Aux consumption; Aux imports
PE = Aux imports × EF (unless set to No)
A3
Settlement totals (equivalent to POI net export)
Net export at POI
PE = 0
A4
Net metering using bills
Net billed export
PE = 0
A6
PV + storage with auditable PV-only charging and net export
Net export at POI
PE = 0
Chapter 4 - Evidence requirements (minimum)
Evidence item
Minimum expectation
Raw meter/settlement/bill data
Covers full monitoring period; traceable to reported monthly totals.
Meter identification and location
Meter ID(s), POI description, and boundary statement.
Meter QA
Calibration certificates or utility confirmation where applicable.
Grid EF reference
PCS grid EF reference for grid-year used.
Reconciliation workbook (if used)
Raw-to-monthly aggregation with checks and sign-off.
Data gap log
Explains missing data and conservative substitution method.
Chapter 5 - QA/QC and submission
Before submission, confirm all QA_QC checks show PASS.
Save a final copy of the tool as evidence.
Submit the tool file alongside the Monitoring Report and supporting evidence.
Chapter 6 - VVB verification expectations
A VVB will verify that:
Configuration selection matches metering boundary.
Monthly DATA values match evidence.
EF is correct for grid-year.
Data gaps are treated conservatively.
OUTPUT values are reproduced from the tool without manual overrides.